Pier 5 Reconfiguration- Gatwick Airport

Gatwick Pier 5

Gatwick Pier 5
1/1
About project: The purpose of the Pier 5 Reconfiguration project is to increase capacity at the airport’s existing Pier 5 as part of Gatwick Airport’s plans to improve passenger experience. In order to facilitate this operation a new departures corridor is being constructed on top of the existing pier, several aircraft stands and gate rooms are being reconfigured.
Scope of works: Working for Vision Survey as setting out engineer I have been instructed to undertake setting out activities ( PQ concrete, whitelining, kerbs, street furniture), produce drawings, check plans and do as-built surveys.